Tuesday, August 13, 2013

Day 77 - Final Framing

So today, the final framing was done for the corner tub in the master bath, the fireplace, and the basement walls. They also finally installed the front door today as well. The electrician finished things up today and the plumber finished most of his work as well. I had some help tonight wiring the house audio from my cousin Josh. Now all of the speaker wire and cat 5e cable is run for the whole house audio system. I still need to run the cat 6 for the internet, some RCA cables, and speaker wire for the surround sound. I wonder how many more nights this will take...

Corner tub and shower in master bath.

Frame for tub and step.

Shower with ledge.

Shower faucet.

Front door from above.


Framed out fireplace and gas line.

Framed office closet.

Half frame by office window.